Canadian Parking Association - Fall 1997
|
|
|
|
Plaza Parkade (continued) - Repairs were
undertaken recently to the Plaza Parkade parking
structure in Prince George, B.C., using an innovative
application of Advanced Composite Materials (ACM's)
and conventional cast-in-place concrete repair
techniques. The use of ACM's in the strengthening
and rehabilitation of existing parking structures
in North America is emerging as a practical,
cost effective, and durable alternative to conventional
demolition and reconstruction. In this case,
the owner of the structure (the Prince George
Downtown Parking Commission) saved many thousands
of dollars by choosing to reinforce a deteriorated
parking garage deck slab 'in-situ' with Carbon
Fibre Reinforced Polymer (CFRP) strips and sophisticated
epoxy adhesives.
Conventional deck surface repairs were undertaken
in May and June of 1997 at the Plaza Parkade
structure in Prince George, B.C. to correct chronic
surface abrasion and delamination in the area
of the ticket spitter, near the main level entrance.
|
|

Deck slab prior to repairs,
looking up-ramp toward ticket spitter

Existing concrete deck slab after
milling.
Corrosion of rebar / evidence of patching |
| |
|
These repairs involved milling the deck surface,
filling local low spots with non-shrink cementitious
grout, and installing a three component, abrasion
resistant deck membrane system (TDM 1000) supplied
by Sternson's Construction Products Ltd. of Vancouver.
In the course of those repairs, a small walk-behind
concrete milling machine broke through the deck
slab in the area immediately above the ground
level electrical room, exposing a significant
zone of deteriorated concrete.
|
|

Large hole broken through slab
during milling with walk-behind planer |
| |
|
Examination of the 25 year old deck slab revealed
improperly placed and significantly corroded
reinforcing steel and evidence of previous, largely
unsuccessful grout patch repairs. Leakage had
likely been occurring through the slab for some
time, aggravated by the deterioration of the
deck surface and rupturing of the elastomeric
waterproofing membrane at some time in the past.
The deck slab was also found to be approximately
1 ½ inches thinner than the original design
drawings specified, resulting in a 30% loss of
thickness in the immediate area of the damage.
|
|

Detail of hole broken through slab from
northwest corner of electrical room |
| |
|
As an alternative to conventional demolition
and reconstruction of the concrete slab (which
would have involved extensive concrete removal,
shoring and forming) the Prince George Downtown
Parking Commission elected to use a system of
Advanced Composite Materials (ACM's) to strengthen
the slab in place.
|
|

Exposed slab soffit in storage room after
removal of drywall ceiling and insulation |
| |
|
In this case, Carbon Fibre Reinforced Polymer
(CFRP) tow sheets were used in conjunction with
epoxy resins to increase the strength of the
slab by direct application to the deck soffit
(underside). Surface preparation and application
of the resins and tow sheets were in accordance
with recently developed technical specifications
for Advanced Composite Materials, provided by
AutoCon Composites Inc. of Toronto.
|
|

Surface preparation underway
removal of paint and surface laitance |
| |
|
Design of the repairs, supervision of the construction
and certification of the final installation to
the local Building Inspection Authority were
provided by Scouten & Associates Engineering
Ltd., of Prince George, B.C.
In this application, the following specific
materials (as supplied by AutoCon Composites
Inc.) were incorporated into the repairs:
- FTS C1 - 20 High Tensile Carbon Fibre Tow
Sheet (505,000 psi tensile strength)
- FP - NS Standard Epoxy Primer
- FR - E3P Standard Epoxy Resin
After repairing the large hole conventionally
with non-shrink grout, and preparing the slab
soffit with simple hand tools (electric grinding
wheels and wire brushes) the strength of the
deck was restored by the EXTERNAL application
of the carbon fibre sheets.
|
|

Primer and adhesive resin batched
by weight to manufacturer's specs

Carbon fibre tow sheet pressed
into adhesive resin by hand |
| |
|
High modulus epoxy resin was used to impregnate
the fibre sheets, and bond them securely to the
slab soffit in the direction of principal flexural
tension. The resulting rehabilitated deck slab
has all the strength and durability required
of a parking structure in a relatively aggressive,
northern Canadian environment.
All site work was undertaken by Wayne Watson
Construction Ltd. of Prince George, B.C., under
a simple Extra Work Order to the original deck
surface repair contract.
The applicators had no previous experience with
in-place concrete restoration using Advanced
Composite Materials, but were competent and enthusiastic
throughout. In our opinion, additional repairs
to facilities owned by the Prince George Downtown
Parking Commission and other parking authorities
could be undertaken in the same fashion by similarly
qualified general contractors, with appropriate
supervision provided by a qualified structural
rehabilitation consultant.
|
|

Tow sheet impregnated with adhesive
resin with "de-foaming" rubber-roller

Tow sheets doubled
up and closely
spaced in area of large hole |
| |
|
Additional information on the practical use
of Advanced Composite Materials in the strengthening
and rehabilitation of existing parking structures
may be obtained from: Scouten & Associates
Engineering Ltd.
|
|

Completed top side repairs |
| |